2024 Library Bond Project Updates

Children at Leesville Library

In 2024, voters passed a $142 million bond for Wake County Public Libraries.

Current Status

Learn about the status of current projects and progress that's been made so far. Please check back, as timelines may change due to factors such as vendor availability and other needs.

View the current status of approved projects:

Project Estimated Opening Date Status
Richard B. Harrison Community Library 2028 Future Project
Athens Drive Community Library 2028 Land Acquisition
Library Administration Building 2028 Future Project
Rolesville Community Library 2028 Future Project
Express Library – Fayetteville St. 2028 Future Project
Southgate Community Library 2028 Land Acquisition
Green Road Community Library 2029 Future Project
Friendship Community Library 2029 Land Acquisition
Zebulon Community Library 2030 Future Project
Leesville Community Library 2030 Future Project
Southeast Regional Library 2031 Future Project
Wendell Community Library 2032 Future Project
Northeast Regional Library 2032 Future Project
Fuquay-Varina Community Library 2033 Future Project

Status options: Future Project, Land Acquisition Phase, Community Engagement Phase, Planning & Design Phase, Construction Phase

Project Descriptions

Select a category below to learn more about the details of current projects.

New Libraries (total $67.1 Million)

Goal: Increase the number of Wake County residents who have a public library within a 10-minute drive of their home.

  • A new community library in Rolesville: Rolesville is the only municipality in Wake County that doesn’t currently have a library, and it is one of the fastest-growing communities. The design would include a Peace and Justice Memorial.
  • A new community library in the Friendship area of Apex: This library would help meet the needs of the area’s growing population.
  • Replacement of the Athens Drive Community Library: When the Wake County Public School System begins renovation of Athens Drive High School in 2026, a new library will need to be built to serve this area.
  • Replacement of the Wendell Community Library: The smallest library in the system is no longer adequate to serve the rapidly growing Wendell population.
  • Replacement of the Southgate Community Library: Replacement of this library with a larger stand-alone facility will better meet the needs of the population of southeast Raleigh.

Library Expansion (total $12.3 Million)

Goal: Meet the demands of population growth on library service.

  • Expansion of the Fuquay-Varina Community Library: In fiscal year 2024, this library has seen the highest circulation of all community libraries—and even more than several regional libraries. This will expand the facility from a community library to a regional library.

Existing Library Renovations (total $43.3 Million)

Goal: Address aging facilities, building system upgrades (such as heating, ventilation, air conditioning and roof replacement), furniture and other enhancements.